818 Bourke Street, Melbourne

Projects Fitout 818 Bourke Street, Melbourne

Renascent were engaged on a Lump Sum arrangement to construct the Hines End of Trip Facility. The 8 week project consisted of new female and male amenities, showers, change rooms and bike storage to existing back of house area.

Works involved the demolition of existing building structure, installation of new partition framing, construction of new raised floor, new electrical, hydraulic and mechanical services as well as alterations to existing fire services and finally installation of new floor finishes and bike racks. New lockers were also installed along with toilet /shower partitions and new joinery units.

Location
Bourke Street, Melbourne VIC

Delivery Method
Lump Sum

Client
Hines Properties

Designer
Gray Puksand

Value
$900K

Floor Area
500 m2